Cargo ships at Tangshan Port are given a "green light" upon arrival.
In the early morning, the cold wind was biting, and the container terminal of Tangshan Port, under the jurisdiction of Hebei Port Group, was bustling with activity. "The vessel 'Zhonghong 68' is 20 nautical miles away from the berth; all positions should be ready as planned," said Chang Xiaoliang, the duty supervisor of Tianjin Tangshan Container Company of Tangshan Port Industrial Group (Tang Port Group), as he stared intently at the green dot slowly moving on the screen and picked up the walkie-talkie.
At this moment, a cargo ship loaded with containers was heading towards the terminal. Unlike usual, this ship did not anchor at the anchorage to wait.
"Direct docking!" At 10:20, when Chang Xiaoliang issued the command, the quay cranes at the terminal were already prepared. The vessel's entry into the port, docking, and unloading proceeded with a "green light" all the way.
Behind the efficient operations is the green wave shipping route piloted by Tang Port Group since August this year. "Just like the green wave sections on city roads, we've created a green wave shipping route, allowing cargo ships to dock upon arrival, start operations upon docking, and leave upon completion—minimizing waiting time," said Zhang Xinliang, Deputy Director of the Production Operations Department of Tang Port Group.
In the past, cargo ships arriving at the port often had to wait at the anchorage for berths, loading equipment, and paperwork, sometimes for over ten hours. Now, Tang Port Group has designated Tianjin Tangshan Container Terminal as the first pilot terminal and Antong Logistics' premium route as the first pilot shipping route. Through prearranged planning, reverse scheduling, and optimized port logistics, they have eliminated "waiting" from the process.
"From the moment the ship sets sail, all aspects—waterway, pilotage, tugboats, berths, and storage yards—are prepared, activating the 'green light mode'," said Zhang Xinliang. According to him, the secret to efficiency lies in port and shipping coordination, with the key being thorough preparation before the cargo ship's arrival.
48 hours in advance: confirm arrival time; 24 hours in advance: reserve berths at the terminal and organize operational resources; 12 hours in advance: issue the port entry and exit plan, prioritizing waterway time slots; 4 hours in advance: all parties enter a dynamic fine-tuning phase to instantly relay updates on weather, tides, and the progress of preceding vessels...
On the scheduling screen, a reverse timeline clearly displays the precise time nodes for each operational stage. "Even while the ship is still at sea, we already know the exact time it will dock, start work, and complete loading and unloading operations. This allows us to position the machinery half an hour in advance, and port vehicles are arranged in order according to the unloading sequence," said Zhang Xinliang confidently about the operational planning.
This confidence stems from years of production scheduling experience, but more importantly, from meticulous reverse calculation. Staff first estimate the expected completion time based on container volume and operational efficiency, then work backward to time-node planning for departure, start of operations, and docking.
"Simply put, it's about coordinating ships, cargo, berths, and equipment in an integrated manner. Previously, each department managed its own tasks independently; now we reverse-plan schedules so the process is mapped out up to departure before the ship even arrives," explained Zhang Xinliang with an analogy, likening the current operations to a relay race, where each team swiftly takes over the baton.
Since the implementation of the green wave shipping route, the direct docking rate of cargo ships on the main route at Tang Port Group has increased from 55.8% to 80%. The average waiting time for a berth has decreased from 9.55 hours to 6.37 hours, while the average departure delay has shortened from 4 hours to 2.93 hours. "The data demonstrates that this 'port-shipping coordination and reverse pre-control' scheduling method is both effective and replicable," said Zhang Xinliang, noting that this method is gradually being promoted to container subsidiaries throughout Tang Port Group.
-
Cargo ships at Tangshan Port are given a "green light" upon arrival.3347
-
Green Sailing Embarks on a New Journey, Intelligent Innovation Shapes the Future: 2026 China Maritime Academic Conference Held in Jining, Shandong4333
-
The Tianjin Port and Shipping Administration Bureau guarantees LNG unloading operations.4408
-
Nantong COSCO Kawasaki was selected for the national leading-level intelligent factory cultivation list.4758
-
November 18 International Shipping Trends6098